Late Delivery of Vacant Possession: Claiming LAD

A late delivery LAD claim starts with a simple fact: a developer handing over the keys late is not merely inconvenient. It breaches the date written into the statutory agreement, and that agreement already sets out what the developer owes for every day of delay. LAD is not compensation you have to persuade the developer […]

Updated 8 November 2026 · Written and reviewed by Nur Nabilah Binti Mohd Aris

Peguam menerangkan kes kepada rakan sekerja
Quick answer

Liquidated ascertained damages are already in the statutory agreement at 10 per cent per annum on the purchase price, calculated daily. You do not have to prove actual loss. The period runs from the date the booking fee was paid, not the date of the sale and purchase agreement, following the Federal Court in PJD Regency. Claims up to RM50,000 are filed by the buyer at the Homebuyer Claims Tribunal, from RM10, within 12 months.

What this late delivery lad guide covers

What the guide on late delivery lad covers

A late delivery LAD claim starts with a simple fact: a developer handing over the keys late is not merely inconvenient. It breaches the date written into the statutory agreement, and that agreement already sets out what the developer owes for every day of delay.

LAD is not compensation you have to persuade the developer to give

Liquidated ascertained damages, or LAD, are already built into the statutory sale and purchase agreement. You do not have to prove actual loss, produce receipts for rent on temporary accommodation, or negotiate the amount. The figure is worked out by formula.

The rate in the statutory agreement is 10 per cent per annum on the purchase price, calculated daily until vacant possession is delivered. The clause number differs between Schedule G for landed property and Schedule H for strata units, so check the clause in your own agreement.

A worked example. A house priced at RM450,000 delivered 122 days late: RM450,000 times 10 per cent times 122 divided by 365, which is about RM15,041. That is not an estimate. It is the same formula the Tribunal applies.

Late delivery LAD: from which date the delay is counted

This is the point developers and buyers most often disagree on, and it can be worth several months of LAD.

Developers usually count from the date printed on the sale and purchase agreement. The Federal Court in PJD Regency Sdn Bhd v Tribunal Tuntutan Pembeli Rumah [2021] 2 CLJ 441 held otherwise. Because collecting a booking fee before the statutory agreement is signed is prohibited under Regulation 11(2) of the Housing Development (Control and Licensing) Regulations 1989, the developer cannot rely on the agreement date. The period runs from the date the booking fee or deposit was paid.

So the first step is to find your booking fee receipt. If you paid the booking in March but the agreement was only signed in August, those five months count. See also our developer booking form guide for the background to that regulation.

The other end of the calculation is the date of valid delivery of vacant possession, not the day you collect the keys at the management office. A handover unaccompanied by the documents it should carry can be disputed.

Did you know

The delay is counted from the date the booking fee or deposit was paid, not from the date printed on the agreement. Find your booking receipt first, because those months count.

Tribunal or court

The Homebuyer Claims Tribunal is designed for buyers to file themselves. These are the figures.

Item Homebuyer Claims Tribunal
Claim limit RM50,000 per claim
Filing fee From RM10
Filing deadline 12 months from the CCC, from expiry of the defect liability period, or from termination of the agreement
Lawyers Not permitted to represent, unless complex issues of law are involved
Time to decision Usually within 60 days
These figures can change. Confirm with the Tribunal before filing.

Two things commonly cause trouble here. First, if your LAD exceeds RM50,000, you cannot split one claim into two to fit under the cap. The choice is to give up the excess and stay at the Tribunal, or go to the civil courts with the full claim. On a RM450,000 price, the RM50,000 cap is reached at around 400 days of delay.

Second, the 12 month period is short and it does not start on the day you collect the keys. It starts from the CCC, from expiry of the defect liability period, or from termination of the agreement, whichever applies.

Who can use the Tribunal

  • A buyer under a statutory agreement: Schedule G or I for landed property, Schedule H or J for strata units
  • The developer must hold a valid housing developer licence and advertising and sale permit
  • This includes a person who bought the unit from the first purchaser

The full text of the Housing Development (Control and Licensing) Act 1966 and the regulations under it can be checked on the Laws of Malaysia portal.

What is not included: a subsale between individuals, because a Tribunal claim lies against the developer and not against a private seller. Commercial and industrial property is also outside the Tribunal jurisdiction. If the developer is unlicensed, the position is different altogether and has to be assessed separately.

Want certainty for your own case?
Every matter has details that differ. Send a short summary and we will tell you what is involved.
WhatsApp us

Defects after handover: the defect liability period

LAD and defects are separate matters, but their filing deadlines are connected.

The defect liability period in the statutory agreement is 24 months from the date of delivery of vacant possession. Within that period the developer is responsible for making good defects you report in writing.

For defect claims, the Court of Appeal in the Lakefront Residence decision of 16 February 2024 confirmed that the 12 month window to file at the Tribunal runs from the expiry of the defect liability period, not from the date you received the keys. That gives more room than most people assume.

So do not stop reporting defects merely because the developer is slow to act. Every written report within that 24 month period is a record, and the record is what you will need later.

Documents to gather for a late delivery LAD claim

  • The booking fee receipt and booking form, because that date decides where the calculation starts
  • The complete statutory sale and purchase agreement, including the payment schedule
  • The notice of delivery of vacant possession from the developer, with its date
  • The Certificate of Completion and Compliance, or evidence of the date it was issued
  • All correspondence with the developer about the delay
  • The list of defects reported and the date of each report

Gather these now, not when the 12 month window is nearly up. Most late delivery LAD claims that fail, fail on documents rather than on merit. Missing documents are the most common reason a well founded claim ends up weak.

If the developer does not comply with the award

A Tribunal award is not a suggestion. If the developer does not pay, you file a Notice of Non-Compliance with the Tribunal, which then sends a copy of the award to the Magistrates Court to be recorded. After that, action can proceed under ordinary court procedure.

Non-compliance with an award is also an offence. The penalty is a fine of between RM10,000 and RM50,000, imprisonment of up to two years, or both.

What most often causes a late delivery LAD claim to fail

  • Filing after the 12 month window has closed
  • Counting from the agreement date when the booking receipt shows an earlier one
  • Signing a settlement letter from the developer without reading the release of claims inside it
  • Filing a claim above RM50,000 at the Tribunal without formally giving up the excess
  • Filing a commercial property matter at a Tribunal whose jurisdiction covers residential housing only

The third is the most common. Developers sometimes offer a goodwill payment lower than the actual LAD, on condition that you sign a full release. Work out your LAD before signing anything, because once the release is signed the balance is gone.

What clients say

I appointed them to handle my parents property matter and everything was handled smoothly and professionally. She explained everything clearly, was very patient with all of our questions and kept us updated throughout the process.

Athirah Azham · Google

Patient, takes the time to explain every term and procedure in detail, and has been very efficient in providing timely updates throughout the process. Whether you are purchasing a home for the first time or have been through the process before.

Aifa Azmi · Google

Excellent service throughout my property transfer transaction. The conveyancing team was professional, responsive, and efficient, keeping me informed at every stage.

Marina Mardi · Google

Rated 5.0 from 9 Google reviews.

Frequently asked questions about late delivery lad

What is the LAD rate?

10 per cent per annum on the purchase price, calculated daily until vacant possession is delivered. The clause number differs between Schedule G and Schedule H, so check your agreement.

From which date does the calculation start?

From the date the booking fee or deposit was paid, not from the date of the sale and purchase agreement. That is the Federal Court decision in PJD Regency Sdn Bhd v Tribunal Tuntutan Pembeli Rumah [2021] 2 CLJ 441.

What is the Tribunal claim limit?

RM50,000 per claim. One claim cannot be split into two to fit under the cap. Above that, the choice is to give up the excess or go to the civil courts.

How long do I have to file?

12 months, running from the Certificate of Completion and Compliance, from expiry of the defect liability period, or from termination of the agreement, whichever applies.

Do I need a lawyer for the Tribunal?

Lawyers are not permitted to represent parties at the Tribunal unless complex issues of law are involved. It is designed for buyers to file themselves.

The developer offered a goodwill payment. Should I accept?

Work out your LAD first. A goodwill offer usually comes with a full release of claims, and once that is signed the balance of the claim is gone.

Still have a question about your own matter?
This guide is general information. Every matter has different details. Send us a short summary and we will reply.
WhatsApp us

Ready to start your property matter?

An initial consultation with no obligation. Tell us about your matter and we will explain what is involved and what it is likely to cost.

No 1, Jalan Setia Dagang AL U13/AL, Setia Alam, 40170 Shah Alam, Selangor
014-4004293 · Monday to Friday, 9:00am to 5:00pm

SEO optimized by Lesgo Media